Context
Vivodyne runs robotic labs that grow and test human tissue at scale for drug discovery: custom robotics, perfusion, imaging and incubation hardware, plus the software that runs and analyzes studies. Each system arrives from a contract manufacturer and has to be brought up and commissioned before it can run studies.
What I did
- Brought 9+ systems from contract-manufacturer hand-off to production-ready, across three hardware iterations.
- Wrote the company’s factory acceptance test (FAT) specification and workflow, which covers about 75% of system commissioning.
- Set up FAT on-site at the contract manufacturer and mentored a junior engineer there until they could run it on their own.
- Wrote bring-up automation scripts and a hardware verification suite with one-click component-level checks, used on every system from the third onward.
- Did extensive hands-on electronics debugging across power, control and sensor subsystems.
Outcome
- Bring-up and commissioning went from 3 months to 2 weeks, then 1 week, then 2.5 days.
- Running FAT at the contract manufacturer raised the company’s quality and reliability expectations for incoming hardware.